Feature #36

automatic changing of screens

Added by Henk van den Berg 387 days ago. Updated 379 days ago.

Status:Closed Start:08/15/2009
Priority:High Due date:
Assigned to:Armindo Antunes % Done:

100%

Category:General
Target version:v0.9.11.0
Vote: 0

Description

When you click on a project, it switches to the 'Edit details' screen for that project.
When you click on a task, it doesn't switch to the 'Edit details' screen for that task, but to the report view.
I would suggest that clicking a project would make the program switch to the report view.
Both the project and the task have their own buttons to switch to their 'edit details' screen.
I feel it would increase intuitiveness if the report view would appear if you click on a project, because that way you can click a project, then immediately click the Start button and record time on that project.
It's more common to switch to a different project and start/continue working on it, than it is to edit the project details.

Associated revisions

Revision 33
Added by Armindo Antunes 382 days ago

+ TABLE_DETAILS id
+ move to other project
  • fixed: #32
  • control project and task new/edit with a tag
  • "Idle time checker" text
  • changed icon for edit task or project
  • improved refreshline
  • doCopy output format changed
    + Log when deleting expired items
    + started doPaste()
    + improve edit start/stop #37
    - Selecting a project doesn't go to edit Project #36
    ________________________________________________
    Closes: #36
    Closes: #37
    Closes: #32

History

Updated by Henk van den Berg 387 days ago

Oops, sorry for selecting 'High', meant to select 'Normal'

Updated by Armindo Antunes 387 days ago

  • Target version set to v0.9.11.0

I agree :)
Should be changed in the next release

Updated by Armindo Antunes 379 days ago

  • Status changed from New to Closed
  • % Done changed from 0 to 100

Also available in: Atom PDF